Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors

Darien’s Shoe Factory Pump Station Was Clogged

Crane Pumps & Systems
Crane

Darien’s Shoe Factory Pump Station Was Clogged

MUNICIPALITY OVERVIEW: The municipality of Darien is located in McIntosh County, GA with a population of approximately 2,000 people and is located 50 miles south of Savannah. Darien has close to 20 waste water pump stations and has a wastewater treatment plant with a 0.6 MGD capacity. The municipality was experiencing consistent pump clogging issues at the Shoe Factory pump station. The Shoe Factory pump station was the most problematic station for the city as its traditional solids handling non clog pumps were clogging every couple of weeks.

LIFT STATION DETAILS: The Shoe Factory pump station is a duplex station with two 10 HP submersible solids handling non clog pumps. The station receives inflow from a nearby law enforcement facility and various motels, and discharges directly to the waste water treatment plant. Both pumps in the station were frequently clogging due to non-flushable solids including bedsheets, clothes, towels, deodorant bottles and shampoo bottles. Clogs up to 3 feet in size were often found clogging the pumps. Solids loading was so severe that according to Wayne Johnson, Darien’s Public Works Supervisor, “the well looked like a garbage dump and that a person can literally walk over the waste water”. There were instances when both pumps in the station would clog and the city had to bypass the station completely. This persistent clogging problem required the city maintenance team to monitor the station continuously to keep the pumps running.

Crane

SITHE installation

INSTALLATION: Darien worked with Pump & Process Equipment, Barnes’ municipal distributor in Georgia, to install a 4″ 10HP SITHE Chopper pump in the station in June 2018. The pump has not clogged since installation. The municipality is so impressed with the SITHE Chopper solution that they are planning to replace other problematic pump stations with SITHE Chopper pumps.

KEY TAKEAWAYS

PAIN POINTS:

  • The pumps in Darien’s Shoe Factory pump station were clogging every two weeks
  • Non-flushable solids including bedsheets and deodorant bottles were clogging the pumps
  • Sometimes, both pumps would clog at the same time requiring expensive bypasses

SOLUTION:

  • Darien installed a 4″ 10HP Barnes SITHE Chopper pump in the station in June 2018
  • The SITHE pump has not clogged once since installation
  • Darien plans to replace other problematic pumps with SITHE Choppers in the future

 

Related Articles

Crane variable speed frequency drives Quick Start Guide

VFD Quick Start Guide

Using variable speed/frequency drives on wastewater pumps can be tricky, but if the drives are sized and programmed properly, they…

Related Whitepapers

Performance Prediction: A Unique Approach for the Aftermarket

Hydro’s software has allowed CFTurbo to improve the optimize the performance of equipment and its fit to its system to make dramatic efficiency and reliability…

Corrective vs. Preventive Maintenance: Which is Better?

Corrective Maintenance This is performed only after a failure occurs in the equipment, which can lead to unexpected downtime and costly repairs. Although it is…

Torque Sensors For Any Application

This guide from S. Himmelstein & Company details their torque sensor solutions, designed to meet the demands of any industry. Learn about: Ultra-Precise Spline Drive…

What is Water Hammer and Why It Is Important to Prevent?

Water hammer (or hydraulic shock) is the momentary increase in pressure inside a pipe caused by a sudden change of direction or velocity of the…

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *