Water pumped off New Zealand Highway in time to Build Ocean Wall

AllightPrimax
AllightPrimax

Water pumped off New Zealand Highway in time to Build Ocean Wall

The North Canterbury Transport Infrastructure Recovery (NCTIR) in New Zealand worked with AllightSykes to quickly pump water off State Highway 1 between Blenhiem and Kaikoura, which are areas often affected by earthquakes.

NCTIR’s main objective was to build a concrete retaining wall a little over half a mile long to safeguard the highway from ocean overflow. They contacted AllightSykes about a high volume pump that could remove existing water off the road quickly, so that concrete could be poured within a challenging time frame – in between tides!

Read the whole story!

https://empoweringpumps.com/products/sw150-pumpset/

Related Articles

Related Whitepapers

Arrow Powers Gas Turbine Analysis at Fern Engineering

Fern Engineering, Inc. was contracted by a major refinery to reduce the exhaust gas temperature variations of their gas turbine fleet. According to Hector Bourgeois,…

2027 DOE Efficiency Mandate & The Case for Higher Efficient Motors

The 2027 DOE motor efficiency requirements are bringing important changes to industrial motor applications. In this presentation, ABB’s Courtney Pickett and Stefanie Casimir break down…

ENKA Designs a State-of-the-Art District Heating System for Hamburg’s CHP Plant

Datacor Fathom provided the best solutions in terms of both heat transfer and pressure loss calculations.” – Kerem Algüzey, ENKA Industry: Power Generation Region: Hamburg,…

Refinery Cooling Water System Calibration Using Datacor Fathom

Hydrus Works, LLC needed to recalibrate a large refinery cooling water system containing nearly 600 pipes, 492 junctions, and 127 heat exchangers. Over 700 pressure,…