Pump Upgrades Helped The City Of Kelowna Save Money And Time

Pumps & Operations
Vaughan PUMP UPGRADES HELP CITY OPERATIONS SAVE MONEY, TIME

Pump Upgrades Helped The City Of Kelowna Save Money And Time

By: Vaughan

The Gyro sanitary lift pump stations in the City of Kelowna, British Columbia were plagued by persistent clogging issues. Like many systems relying on basic non-clog pumps, Kelowna city employees were dealing with service and system operations issues due to the challenges rags ensued on the Variable Frequency Drives (VFDs), slowing the pumps at times of lower station inflow rates.

Then, as one pump plugged, pump flow fell, which caused other pumps to cycle harder to keep up with inflow rates. Eventually, the next pump was also slowed by the VFD, and under this slowed condition it would generally also plug, compounding the issue.

There were many circumstances where all the station’s pumps were plugged or off-line, causing serious cost and operations implications. On average, their outmoded pumps were removed from the pump station for unplugging and cleaning three times per week. Three staff members and a crane truck were required for each maintenance event. Factoring in labor and equipment, maintaining the old pumps cost the city nearly $50,000 USD / $60,000 CAD annually. In 2009, needing an updated, more cost-effective solution, Kelowna Operations decided it was time for an upgrade.

The City of Kelowna purchased one 60 horsepower (hp), 1,180 revolutions per minute (rpm) model submersible chopper pump in September 2009. A newer submersible (rated performance: 2,000 U.S gallons per minute (gpm) at 54.5 feet total dynamic head [tdh]) was installed alongside their older non-clog pumps in an effort to evaluate and improve operating efficiencies. After successful implementation and noticeable improvements, a second submersible pump was purchased in May 2011, and a third in November 2015. Thanks to the ability to reuse the original guiderail system, swapping out the pumps was fast and simple, with no rework required.

Vaughan PUMP UPGRADES HELP CITY OPERATIONS SAVE MONEY, TIMESince replacing their older non-clog pumps with the newer chopper pumps, routine plugging problems in the pump station have been eliminated. “No pump servicing has been required for cleaning (unplugging) of the chopper pumps,” explained Brad Stuart from Kelowna Ops. “The only pump servicing has been related to inspections at appropriate routine maintenance service intervals.”

*Cost-savings calculations: Cost to resolve each plugging event: 3 operators x 2 hours x $40/hr = $240/event labor costs. The cost of the crane truck was $150 for each event. Total cost: $390/ event. With 3 plugging events/ week, cost was 3 x $390 = $1170/ week. With 52 weeks/year x $1170 cost/week = $60,840 CAD/year cost to maintain the old pumps. In US dollars at 2021 exchange rate: $60,840/1.25 = $48,672.

Related Articles

Related Whitepapers

How to Read a Pump Curve (and Why you Want to)

If you have ever worked with pumps before, be it in an installation, maintenance, or engineering capacity, chances are high you have seen a pump…

Design Optimization of Jet Fuel Pump for Aviation

Jet fuel pumps play a critical role in the safe and efficient operation of commercial aviation. The performance and reliability of these pumps directly impact…

The Cost Of Downtime In Manufacturing [Infographic]

Downtime can be the most expensive element of any manufacturing operation. Here are some important facts and tips you should know to cut down on…

AFT Fathom used to Model Central Heating Cycle of a State-of-the-art Combined Heat and Power Plant

Kerem Algüzey, design engineer at ENKA Insaat ve Sanayi A.S., used AFT Fathom to simulate the central heating cycle to inform the design of the…

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *