Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors

Fast rotor repair also improves efficiency

Compressors
Sulzer

Fast rotor repair also improves efficiency

Cracked steam turbine rotor repaired and reinstalled with 8% improvement on performance

When a damaged steam turbine rotor needed to be repaired, a power generation plant in Indonesia turned to Sulzer for an expert service. Rather than wait for at least a year for a new rotor from the original equipment manufacturer (OEM), the plant opted for a repair that took only sixteen weeks. This swift and effective repair also managed to achieve an 8% improvement in efficiency.

The Indonesian geothermal power plant had been experiencing some issues with one of its 60 MW steam turbines. During the previous two years, the pre-existing maintenance provider had repeatedly tried to repair the turbine, but the vibration issue had persisted. Despite several attempts to low speed balance the rotor at their premises, it still exhibited high vibration levels.

Initial investigation

During one of these off-site balancing procedures, the plant engineers discovered deep cracks that were suspected to have been caused by a previous repair by another service company. As well-known experts in the repair of steam turbines, Sulzer was called in to resolve the problem.

Sulzer’s initial inspection revealed that the rotor had cracks on the radius section between the last stage disk and the gland seal area located on both the governor and the generator sides. In addition, there was considerable evidence of erosion on the blades, the disks and the balance correction holes.

Repair re-evaluation

The initial plan was to machine out the material until the cracks were removed and then rebuild the shaft using submerged arc welding before machining it to nominal dimensions. However, after comprehensive inspection at Sulzer, the crack propagation already had a spiral shape through the center of the shaft, making it impossible to machine out the crack area only. Sulzer then came up with a repair proposal that involved designing a stub shaft that would be used to join the two pieces together before the shaft was rebuilt to its nominal dimensions.

Andrianto Hapsoro, Head of Engineering, Sulzer Indonesia, explains: “There was always a customer representative in the workshop, which helped maintain excellent communications and keep them up to date with progress. Any rotor repair is time-critical, with lost revenue making every day count in this project.”

With the location of the repair being so close to the 6th disk, some additional repairs would be needed to this disk, which would extend the overall time to complete the project. in order to save time, Sulzer proposed both stage 6 disks would be removed and possibly reinstated at a later date. This was then agreed by customer.

Repair expertise

Joining two sections of a turbine rotor requires considerable expertise, including computer modelling and finite element analysis (FEA) to ensure that the proposed design would withstand the stresses of normal operation. The FEA was also carried out at an overspeed of 3’600 rpm to ensure that the centrifugal loading on the disks would not cause any damage to the rotor shaft after the repair. With all the necessary analyses completed, the machine shop started to prepare the two rotor shaft sections for the addition of the stub shaft.

Sulzer

The stub shaft was shrink-fitted to the shaft before being welded in place.

In-house precision machining enabled the stub shaft to be shrink-fitted into the prepared connections before the whole joint area was preheated prior to the welding process. Using precision-controlled, submerged arc welding equipment, the stub shaft was built up to a level that would allow it to be machined back to the required dimensions. Once the original dimensions had been achieved, a series of non-destructive tests (NDT) was carried out to ensure there were no flaws in the completed rotor assembly.

Sulzer

Precision machining was required to ensure a perfect fit.

These processes were repeated to remove the cracks in the thrust end of the rotor as well, bringing the completed assembly back to finished dimensions. Once all the machining was complete, the rotor was dynamically balanced before being shipped back to the customer.

Improving performance

While the repairs were being completed on the rotor, the field service team was working at the customer’s site to repair the diaphragm and improve the sealing of the casing. This work would be influential in improving the efficiency of the steam turbine.

Prior to the project being started by Sulzer, the turbine required 393 tonnes of steam per hour to produce the 53.4 MW of energy. Despite one set of disks being removed, the repair to the static and rotor components of the turbine delivered by Sulzer, enabled it to maintain an output of 55.1 MW but using only 374 tonnes per hour of steam, which is an 8% improvement in efficiency.

When the repaired turbine rotor arrived back on site, the field service team carried out the installation and commissioning, which included vibration testing at full load. All the results were well within the original specifications and the generator has remained at full capacity ever since.

Andrianto concludes: “The customer was very impressed with the results of this project. In total, the whole repair took only 16 weeks, which is considerably less than the estimated lead time for a new rotor from the OEM, which is closer to 52 weeks.”

About Sulzer:

Sulzer, headquartered in Winterthur, Switzerland, since 1834, specializes in pumping solutions, services for rotating equipment, and separation, mixing, and application technology. Sulzer provides cutting-edge maintenance and service solutions for rotating equipment dedicated to improving customers’ processes and business performance. When pumps, turbines, compressors, generators, and motors are essential to operations, Sulzer offers technically advanced and innovative solutions. The company creates reliable and sustainable solutions for its markets: oil and gas, power, water, and general industry. Sulzer serves customers around the world through a network of over 180 production and service sites, and it has a strong footprint in emerging markets. In 2016, the company achieved sales of roughly CHF 2.9 billion with around 14 000 employees. www.sulzer.com.

Related Articles

Compressor Maps in AFT Arrow

Compressor Maps in AFT Arrow

In AFT Arrow, a compressor map enables a more precise modeling of a centrifugal compressor junction across its complete range…

Related Whitepapers

Five Reasons To Choose A Bearingless Torque Sensor

Benefits that improve your torque measurements Best real-world accuracy Highest Overload Highest Overrange

Advanced Sealing and Condition Monitoring Strategies In Water and Wastewater Plants

Introduction As a plant/maintenance manager or reliability engineer for a water or wastewater facility, you want to know about the best technologies to help your…

Downthrust Measurement in Vertical Pumps Prevents Failure: The Benefits of Measuring Axial Force in Real-Time

“Himmelstein’s Thrustmeter has proven to be accurate and repeatable, which are two of the main things that define quality in an instrument. It’s been a…

Electricity, Power, and Emissions: Using Motor Power Data to Create a Climate-Informed Maintenance Plan

Take Action Today To Make Your Pumps More Efficient Pump motor power levels and energy consumption provide valuable input about the status of and changes…

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *