Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors

Who are you going to call? Going beyond standard procedure

Power & Energy
Sulzer Who are you going to call Going beyond standard procedure

Who are you going to call? Going beyond standard procedure

By: Sulzer

Rapid boiler feed pump repair and root cause analysis ensure power generation reliability

At a time when national electrical grids are under extreme pressure, unexpected outages can prove to be a considerable challenge. When a power plant in Germany experienced the sudden failure of a boiler feed pump, output dropped by more than 40%, which affected both the local grid and company profits. Needing to resolve this situation urgently, Sulzer was called in to repair the asset and conduct an investigation to secure the reliability of the power station.

Thermal power plants rely on boiler feed pumps to supply large volumes of pressurized water to create the steam that drives the turbines. Keeping these vital assets in good order requires personnel to follow detailed operating procedures and planned maintenance programs. Following on from the failure of the first pump in this particular power station, the worry of a second pump suffering from the same problem and ensuring overall reliability meant root cause analysis was as important as getting the facility back to full capacity.

Finding fast repairs saves lost profits

The power plant in question has two boiler feed pumps that have been in service for approximately 10 years without any issue. However, recently, the operator noticed a problem with the mechanical seals and called in Sulzer. The company responded immediately with specialist field service personnel on site the next day. Further investigation revealed that the pump was seized as a result of not following the correct start-up and maintenance procedures.

While the boiler feed pump was out of action, productivity from the plant was significantly reduced. Although the lost output from the power station was covered by other sites, the profit loss ran into multi-millions of Euros for every week the pump was out for repair. Considering the current demand for energy across Europe, time was most certainly of the essence.

“The first task was to explain to the plant management how the project would be delivered and the timeframe involved,” explains Claudia Calies, Service Center Manager for Sulzer. “Clearly, the pump was required back in service in the shortest time possible and we have to manage this expectation and provide an accurate timeline for the work to be completed.”

Sulzer Who are you going to call Going beyond standard procedure

The initial investigation found that the balance piston and sleeve were welded together and this would require the shaft to be cut off and drilled out to separate the part

Putting in a double shift

From the first field service personnel on site to the last commissioning engineer leaving, Sulzer’s global network of technicians, engineers, designers, logistics specialists and project managers combined their OEM knowledge and service expertise to resolve this issue. Due to the high water pressures involved, the pipe connections to the pump are welded, requiring a specialist to disconnect the 10-tonne pump. Once this was complete, the pump was removed and transported to Sulzer’s service center in Jänschwalde to enable the necessary repairs to be completed.

The initial investigation found that the balance piston and sleeve were welded together and this would require the shaft to be cut off and drilled out to separate the parts. The piston was replaced while a boring machine was used to bore out the sleeve to its original dimensions and complete the repair.

The Jänschwalde service center staff worked two shifts per day to minimize the time required to get the pump back up and running.

A spare on-hand is worth two on order

The plant operator had a stock of spare parts, including a new pump rotor, which had been ordered at the time of the pump’s installation. Considering the age of the rotor, it was sent to Sulzer to be inspected and to confirm its suitability for installation after 10 years in storage.

The repaired balance piston was then fitted together with the spare rotor, which had passed its inspection. All the additional spare parts required for the repair were also on-hand having been ordered for urgent delivery.

“Due to the important role of the pump, the power plant needed to have extensive documentation completed detailing all of the work carried out. This included independent checks and x-ray inspection of the new welds when the pump was reinstalled. The complex details involved in the repair of key pieces of equipment go far beyond the physical repair work, but Sulzer’s experience in maintaining all rotating equipment means that every aspect is covered in a turnkey project.”

Sulzer Who are you going to call Going beyond standard procedure

The pump was removed and transported to Sulzer’s service center in Jänschwalde to enable the necessary repairs to be completed

The root cause bubbles up during inspection

With the power plant running two of these pumps, the operator was very keen to identify the root cause of the initial problem to enable any additional preventative measures to be taken. During the inspection, there was evidence that a steam bubble was present in the area around the balance piston, indicating a lack of cooling and lubrication, which led to a massive rise in temperature.

Some information that was missing during the initial investigation was that the plant suffered an unexpected shutdown two or three days before the pump failure took place. Once the reason for the shut-down was resolved, the pump was restarted, however, during this process a procedural issue was determined as the root cause of the subsequent pump failure, confirming the operational reliability of the pump.

As a result, having reinstated the pump and recommissioned it, Sulzer offered additional training for the plant personnel to try and prevent any reoccurrence in the future.

Sulzer Who are you going to call Going beyond standard procedure (3)

From the initial stoppage of the pump to recommissioning, the whole project was completed in nine and a half weeks

Stopping pump failure is standard procedure

In total, from the initial stoppage of the pump to recommissioning, the whole project was completed in nine and a half weeks. In contrast, the alternative would have been to order a new pump, but typically such a highly engineered asset would have considerably longer lead time. In an industry where downtime must be kept to an absolute minimum, Sulzer offers fast, responsive solutions that are backed by precision engineering and decades of experience.

Once the pump was reinstalled and operational, a review meeting was held to assess the performance of Sulzer’s team and the results achieved during the project. Although the operator had initially suspected that the pump might be at fault, it was concluded that the incorrect start-up procedure was responsible. The additional training and the checks that were carried out on the second pump have ensured that the scenario will not be repeated and that both pumps will continue to deliver reliable service.

Claudia concludes: “We regularly support the plant with annual shutdowns and communication between us is open and transparent, which is essential for a rewarding relationship.”

Following the successful completion of the project, the original rotor will be refurbished by Sulzer with a new balance piston being fitted along with refurbished impellers. This will enable the power plant to restock the spare part in case it should be needed in the future.

The project in numbers:
• 10-tonne pump
• Up to 12 personnel involved
• Time to complete repair: 9.5 weeks
• Profit lost during downtime: Multi-million euro per week

About Sulzer:
Sulzer is a global leader in fluid engineering. We specialize in pumping, agitation, mixing, separation and application technologies for fluids of all types. Our customers benefit from our commitment to innovation, performance and quality and from our responsive network of 180 world-class production facilities and service centers across the globe. Sulzer has been headquartered in Winterthur, Switzerland, since 1834. In 2021, our 13’800 employees delivered revenues of CHF 3.2 billion. Our shares are traded on the SIX Swiss Exchange (SIX: SUN).

www.sulzer.com

Related Articles

Related Whitepapers

Five Reasons To Choose A Bearingless Torque Sensor

Benefits that improve your torque measurements Best real-world accuracy Highest Overload Highest Overrange

Advanced Sealing and Condition Monitoring Strategies In Water and Wastewater Plants

Introduction As a plant/maintenance manager or reliability engineer for a water or wastewater facility, you want to know about the best technologies to help your…

Downthrust Measurement in Vertical Pumps Prevents Failure: The Benefits of Measuring Axial Force in Real-Time

“Himmelstein’s Thrustmeter has proven to be accurate and repeatable, which are two of the main things that define quality in an instrument. It’s been a…

Electricity, Power, and Emissions: Using Motor Power Data to Create a Climate-Informed Maintenance Plan

Take Action Today To Make Your Pumps More Efficient Pump motor power levels and energy consumption provide valuable input about the status of and changes…

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *