Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors

AFT Fathom™ Instrumental in Re-configuring Office Building HVAC System

Applied Flow Technology

AFT Fathom™ Instrumental in Re-configuring Office Building HVAC System

Swanson Rink was tasked with increasing the airflow for the second floor of a two-story office building as part of a remodeling project. The remodel would increase the office building’s occupancy, leading to a rise in cooling demands.

The east side of the building is served by an air handling unit (AHU-1), and the west side of the building is served by a second air handling unit (AHU-2). Increased cooling is typically provided by raising fan speed. However, the AHUs serving this space were already operating close to their maximum airflow rate and did not have the capacity to increase the fan speed significantly.

Product performance data for the AHUs and fans was unavailable, so there were no fan curves to determine if the fans could accommodate the increased airflow.

Rory Heim, mechanical engineer at Swanson Rink, used AFT Fathom in conjunction with a thermal loads program to analyze the fan performance required by different load configurations.

The thermal loads program used the standard 55 F (13C) supply air temperature to condition the space and calculated the required  cubic feet per minute (CFM). Heim then modeled the system in AFT Fathom using the calculated airflow rate values to determine the new desired operating points for each AHU fan (see  figure 1 above).

When the static pressure and airflow rates of each AHU were measured, Heim determined the real static pressures were too  low compared to the AFT Fathom model’s desired pressures at the same flow rate.

“AFT Fathom allowed us to accurately determine the minimum system conditions we needed for a functional design,” said Heim. “When those minimum system conditions—CFM/static pressure—couldn’t be met by existing equipment, AFT Fathom allowed us to rapidly evaluate different strategies to satisfy the restricting design parameter—fan performance.”

To remediate the airflow rate issues, Heim performed a simulation in the HVAC load calculation program. The supply air temperature of the AHUs was reduced in the program from 55 F to 50 F (13 C to 10 C). This determined the space would require 75% airflow for the same amount of cooling. The lower airflow requirements allowed the fan to provide a higher static pressure.

With this lower supply air temperature, AFT Fathom predicted AHU-1’s requirements to be 19,695 CFM (558 m3/min) and 1.15 in. water (29.2 mm water). AHU-2’s requirements were predicted to be 22,952 CFM (650 m3/min) and 1.48 in. water (37.6 mm water).

While visiting the site, Heim discovered a static pressure sensor at the outlet of each AHU. He had the building engineer set each AHU fan close to the desired CFM values and report the airflow and static at that operating point.

The reported operating points for AHU-1 were 22,502 CFM (637 m3/min) and 1.24 in. water (31.5 mm water); for AHU-2, they were 21,587 CFM (611 m3/min) and 1.36 in. water (34.5 mm water).

Based on these values, Heim was confident that each AHU would be able to deliver the amount of air needed to condition the office building’s second floor.

Heim said that receiving measured field data from existing equipment that closely matched their model data gave the team confidence in the model. It allowed the team to move forward with the assurance that post-construction data would closely match AFT Fathom predicted data.

The project has since been completed and the system balanced to Swanson Rink’s design values. The AFT Fathom model was in close agreement with the installed operating points (see Figure 2). The final operating points were 20,849 CFM (590 m3/min) and 1.03 in. water (26 mm water) for AHU-1 and 25,297 CFM (716 m3/min) and 1.12 in water (28 mm water) for AHU-2.

“If you calculate a percentage error based on our design and the installed operating points, the model may seem inaccurate, but in this case, the model was invaluable in being able to demonstrate that our designed system would perform within the existing fan parameters,” said Heim. “To be within 0.09” (AHU-1) and 0.12” (AHU-2) of static between our desired operating points at 50 F and the BAS (building automation system’s) measured operating points, speaks to the accuracy of our model and the abilities of AFT Fathom to accurately model complicated ducting systems.”

What’s the best way to find out if AFT software is right for you? Try a FREE Demo!

 

Related Articles

Related Whitepapers

Five Reasons To Choose A Bearingless Torque Sensor

Benefits that improve your torque measurements Best real-world accuracy Highest Overload Highest Overrange

Advanced Sealing and Condition Monitoring Strategies In Water and Wastewater Plants

Introduction As a plant/maintenance manager or reliability engineer for a water or wastewater facility, you want to know about the best technologies to help your…

Downthrust Measurement in Vertical Pumps Prevents Failure: The Benefits of Measuring Axial Force in Real-Time

“Himmelstein’s Thrustmeter has proven to be accurate and repeatable, which are two of the main things that define quality in an instrument. It’s been a…

Electricity, Power, and Emissions: Using Motor Power Data to Create a Climate-Informed Maintenance Plan

Take Action Today To Make Your Pumps More Efficient Pump motor power levels and energy consumption provide valuable input about the status of and changes…

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *