Gear Drives Solution For A Large Steel Mill

Motors & Drives
Gear Drives Solution For A Large Steel Mill

Gear Drives Solution For A Large Steel Mill

The screw-down mill stands at a large steel mill in Pennsylvania was experiencing continuous problems with the gear drives. The material of the existing manufacturer’s gear was breaking down, which caused cracks, fatiguing, broken teeth due to inherent designed duty-cycle stresses.

A meeting with the mill’s engineers, purchasing manager, and hot mill managers, was held at Delroyd’s Niagara Falls facility to review the problem and determine why the existing gearing design was failing so rapidly, and what could be done to solve the problem and improve the gearing life.

The Delroyd team reverse-engineered the screw-down gearbox to develop a more robust solution. The bronze gear material was changed to manganese for enhanced yield and overall strength. A larger radius and shot peen process was added to the root of the worm thread hence reducing the root stresses.

The new Delroyd gearbox design extended the gearing life from 3 years to more than 6 years. Based on the redesigned mill stand gearbox success, the customer awarded Delroyd with orders for additional new complete gearboxes, spare worm/gear sets, and additional gearbox rebuilds.

Altra Worm Gear DrivesHighlights
• Large radius added to worm thread
• Manganese gear material for enhanced yield and strength
• Through hardened, ground, and polished alloy steel worm
• Worm thread root was shot-peened to provide stress reduction at the contact zone

Read about more solutions from Altra Industrial Motion.

On March 27, 2023, Altra Industrial Motion was acquired by Regal Rexnord Corp. Learn more about this here.

Altra Worm Gear Drives

Related Articles

Related Whitepapers

Design Optimization of Jet Fuel Pump for Aviation

Jet fuel pumps play a critical role in the safe and efficient operation of commercial aviation. The performance and reliability of these pumps directly impact…

The Cost Of Downtime In Manufacturing [Infographic]

Downtime can be the most expensive element of any manufacturing operation. Here are some important facts and tips you should know to cut down on…

AFT Fathom used to Model Central Heating Cycle of a State-of-the-art Combined Heat and Power Plant

Kerem Algüzey, design engineer at ENKA Insaat ve Sanayi A.S., used AFT Fathom to simulate the central heating cycle to inform the design of the…

Driving Energy Savings a Commercial Facility Energy Upgrade Project

Upgrading to Design Envelope pumps helped GAC save energy costs of 20,000 AED in the first year. Armstrong’s Pump Manager service provides reports and notifications…

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *